SUMMARY OF ACTIVITIES CARRIED OUT
Table 1: Progress of activities

Libel planned activities

Expected results for the quarter (A)

Realization of the quarter (B)

Run rate
(C = B / A)

Variance analysis and comments

 

Validate the beneficiary database

 

194

 

 

145

66,21%

From a total of 194 beneficiaries, 81 gave up for various reasons, the main one being the dissemination of erroneous information about the objectives of the AVEC project and the expected results of its implementation, namely, to acquire and practice, the culture of savings and credit within a Village Savings and Loan Association.
After several sessions of rectification of the information and sensitization, 32 new postulants wished to join and engage consciously and freely in a AVEC.
We obtained approval from PCO-E to integrate them into the beneficiary database.

 

Train beneficiaries in the AVEC methodology

 

194

145

66,21%

To the 113 beneficiaries who did not give up, were added 32 new applicants, now beneficiaries, who have been diligently following all the training courses on the AVEC methodology with the exception of the last module, which deals with the sharing of shares at the end first cycle (09 to 12 months). The latter module will be delivered if the BCP-E decides to close the first AVEC cycle based on the performance of the AVEC and the recommendations that ICA-CI has made.

 

Accompany the AVEC throughout the first cycle

08

08

100%

All 08 WITH were accompanied.However, 03 WITH show reduced numbers to13 (Elibou 2 and Sokrogbo 1) and to 11 (Sokrogbo 2)
For 05 AVEC, we could close this first cycle at 09 months. For the others, however, whose number is significantly reduced, it would be advisable to extend it to 12 months.

 

To evaluate the performance of AVEC after the first cycle

 

08

 

08

100%

At this stage of the process, an evaluation can be done because we will have reached 09 months of activities. For some AVEC with the penalty (03), an extension of 03 months to reach 12 months of operations, could be granted to them, in order to compensate for the delay which they accuse, without however blocking the evolution of those (05) which quickly understood the stakes and the challenges to overcome with AVEC. We evaluated all the 08 AVEC, even those (03) whose performances are limited.

THE RESULTS OBTAINED
Table 2: Monitoring outcome indicators

Code

indicators

CURRENT QUARTER

CUMUL DU PROJET

Forecast (A)

Production (B)

Completion rate (C=B/A)

Forecast (D)

Production (E)

Completion rate (F=E/D)

INDICATORS OF DEVELOPMENT OBJECTIVES

 

 

 

 

 

 

1

Direct beneficiaries of AVEC (men and women)

194

145

66,21%

200

145

72,50%

2

Women direct beneficiaries of AVEC

96

67

46.20%

80

  67

83,75%

INDICATORS OF INTERMEDIATE OBJECTIVES

 

 

 

 

 

 

 

Youth enlisted for Village Savings and Loans Association (AVEC) activities

531

32

06,02%

600

32

05,33%

 

Selected youth

194

145

66,21%

200

145

72,50%

 

Young women selected (at least 40%)

96

67

46,20%

80

67

83,75%

 

AVEC (VSLAs) formalized

08

04

50%

08

04

50%


Table 3: Beneficiary monitoring


LOCALITE

NUMBER PREVUS

YOUNG BENEFICIARIES

IN PROGRESS

ACHIEVED

NOT ACHIEVED

AVEC (VSLAs) SHUTTER

1

Grand-Yapo

50

40

36

_

_

2

Boussoukro

50

43

43

_

_

3

Ellibou

48

33

33

_

_

4

Sokrogbo

46

24

24

_

_

 

TOTAL

194

140

136